PPM Checkpoints-Hot Water Generator |
Use pressonel protective gear and carry out shutdown after aking proper care |
Apply "Lock Out" and "Tag Out" signboard |
Performance Check list |
Check for any loose connection in the panel |
Check and clean connection of switchgears |
Check for any hot spots or overheating within the panel and take appropiatr action |
Blow out dust from the panel |
Check and ensure earth continuty |
Check and ensure correct setting of low level current and fuses |
Measure the load current and compare with rated current |
Check the butterfly valve for operation |