PPM Checklist:-AHU Panel
Performance Check list | ||||
Check for loose connections in the bus bar and tighten wherever required | ||||
Check input & output point of MCCB for heating | ||||
Blow out dust from the cubicle and switchgear | ||||
Check earth system throughly | ||||
Check and ensure correct operation of all the indicating lamps, meters | ||||
Ensure that the cables are not overheated. | ||||
Ensure Three phase current | ||||
Ensure that all indication lamps, Meter working properly | ||||
Ensure that all thimble & connector check for heating | ||||
Check meter for both reading DHVPN & DG | ||||