Standard Operating Procedure- Chiller
Switching "ON" Chiller
|
Check the power supply in Chiller panel on Panel
|
Ensure all necessary valves are in open condition
|
Switch ON the required no. of Primary/ Condersor Pump(s) and cooling tower fan (s)
|
Ensure required no. of Secondary Pumps are started
|
Switch ON the Chiller in auto mode by selecting Auto on display unit
|
Check the inlet and outlet water temperature and all electrical parameters
|
Check and note all parameters
|
Record the readings as per the log sheet and schedule
|
Switching "OFF" Chiller
|
Give Stop command at display unit
|
Check the equipment for stop condition
|
Switch OFF CT fan, Condenser, primary and secondary pumps
|