PPM Checklist:-Light D.B

Check for loose connections in the terminations and tighten wherever required
Check & clean connection of switchgears & replace nut/bolts & cable termination socket wherever required
Check for any sparking spots in TPN/ MCB/ELCB wherever applicable.
Blow out dust from the DB
Check & ensure earth continuity
Ensure that the cables are not overheated.
Ensure that the cables thimble are not overheated.
Ensure current in each outgoing circuit not more than 60% of TPN/MCB/ELCB rating