Sunday 24 June 2012

PPM-Garden Pump


PPM Checklist-Garden Pump
Performance Check list
Check for loose connections in the bus bar and tighten wherever required
Check & clean connection of switchgears & replace nut/bolts & cable termination socket wherever required
Check for any hot spots or overheating within the panel and take appropiate action
Blow out dust from the panel
Check & ensure earth continuity
Check for any sparking spots in TPN/MCB/MCCB wherever applicable.
Check & ensure correct setting of Overload relay and time delay relays
Measure the load current and compare with rated current
Check For ducting motor
Check Indication Lamp
Check Auto/Mannual Switch
Check & ensure Motor connection is tight & not overheated
Remove signboard
Ensure that no tools are left within the cubicle of the panel

No comments: